How to Avoid AB 2143 Prevailing Wage: Save 10-15% on Commercial Solar Costs
Complete guide to avoiding AB 2143 prevailing wage requirements for Southern California commercial solar projects using non-export system designs and legal exemptions.

How to Legally Avoid AB 2143 Prevailing Wage and Save 10-15% on Commercial Solar
California Assembly Bill 2143 has fundamentally changed the economics of commercial solar installation for Southern California businesses. Effective January 1, 2024, this law requires prevailing wage rates for most commercial solar projects, increasing costs by 10-15% and adding significant compliance burdens.
However, there’s a legal pathway to avoid these requirements: non-export solar systems. This comprehensive guide explains how Southern California businesses can save thousands of dollars while still achieving their energy and sustainability goals.
Understanding AB 2143: The Hidden Solar Tax
What AB 2143 Really Means for Your Business
AB 2143 requires prevailing wage rates - often 30-50% higher than market rates - for construction workers on qualifying solar projects. But the real cost impact goes beyond just wages:
Direct Cost Increases:
- Labor rates: 30-50% higher than standard market rates
- Administrative burden: Certified payroll reporting every 6 months
- Compliance risk: Loss of NEM eligibility for violations
- Project delays: Additional paperwork and approvals
Total Project Impact: 10-15% Cost Increase
For a typical 500kW commercial installation costing $625,000, AB 2143 adds approximately $62,500 - $93,750 in additional costs.
Which Projects Are Subject to AB 2143?
The law applies to all commercial solar projects that meet these criteria:
• System size: Over 15kW (AC)
• Property type: All commercial properties, plus multifamily buildings over 2 stories
• Utility territory: SCE, PG&E, or SDG&E (investor-owned utilities only)
• Net metering: Projects using NEM 1.0, 2.0, or 3.0 tariffs
• Application date: Interconnection applications submitted after December 31, 2023
Key Exemptions:
- Residential systems (single-family homes)
- Systems ≤15kW
- Projects in municipal utility territories (LADWP, SMUD, etc.)
- Non-export systems (the focus of this guide)
The Non-Export Solution: Legal AB 2143 Avoidance
Why Non-Export Systems Are Exempt
The key legal distinction is in AB 2143’s language: it only applies to projects that “receive service pursuant to the standard contract or tariff developed pursuant to Section 2827.1” - referring specifically to Net Energy Metering (NEM) tariffs.
Non-export systems:
- Don’t participate in NEM programs
- Never send electricity to the grid
- Consume all solar production on-site
- Are completely exempt from AB 2143 requirements
How Non-Export Systems Work
Non-export systems use certified Power Control Systems (PCS) combined with battery storage to prevent any electricity export to the grid:
- Real-time monitoring: CT meter measures power flow at service entrance
- Battery integration: Excess solar production charges on-site battery storage instead of exporting to grid
- Instant response: If power would flow to grid, PCS redirects energy to battery or shuts down solar production within 2 seconds
- Onsite consumption only: All solar power used for building loads or stored in batteries
- Grid independence: System operates without utility interaction while maximizing energy utilization
Technical Implementation: Power Control Systems
Certified PCS Requirements
To qualify for AB 2143 exemption, systems must use UL 3141 certified Power Control Systems with specific capabilities:
Required Specifications:
- UL 3141 certification (or legacy UL 1741 CRD)
- Import Only Mode capability marked “Y”
- Response time: 2 seconds or less for grid export prevention
- Service point measurement: CT monitoring at main electrical service
Equipment Selection and Expertise
The California Energy Commission maintains an approved equipment list for certified Power Control Systems that meet AB 2143 exemption requirements. Our team has extensive experience installing and configuring PCS-certified equipment from leading manufacturers including SolarEdge, SMA, Fronius, and Enphase systems.
We handle the technical specifications and equipment selection process to ensure your non-export system meets all regulatory requirements while delivering optimal performance for your specific facility needs.
Cost-Benefit Analysis: Non-Export vs. Traditional NEM
Traditional NEM System Costs (AB 2143 Subject)
500kW Commercial Installation Example:
Cost Component | Standard Rate | AB 2143 Rate | Increase |
---|---|---|---|
Installation Labor | $125,000 | $162,500 | +$37,500 |
Electrical Work | $75,000 | $97,500 | +$22,500 |
Administrative/Compliance | $0 | $15,000 | +$15,000 |
Total Project Cost | $625,000 | $700,000 | +$75,000 |
Non-Export System Costs (AB 2143 Exempt)
Same 500kW Installation with PCS:
Cost Component | Non-Export Cost | Notes |
---|---|---|
Standard Installation | $625,000 | Market rate labor |
PCS Equipment Premium | $12,000 | Certified power controls |
Higher Interconnection Fee | $655 | ($800 vs $145) |
Total Project Cost | $637,655 | |
Savings vs AB 2143 | $62,345 | 10% cost reduction |
Break-Even Analysis
For most Southern California commercial projects, non-export systems provide net savings even after accounting for:
- PCS equipment costs
- Higher interconnection fees
- Loss of excess generation credits
Non-export systems with battery storage are ideal when:
- Business wants maximum solar utilization regardless of usage patterns
- Energy resilience and backup power are important considerations
- Demand charges >$8/kW/month make battery storage economically attractive
- Project size >100kW provides economies of scale for integrated systems
Non-Export System Configurations
Configuration 1: Solar + Battery Non-Export System
Best for: New installations, businesses with variable energy usage patterns
Setup:
- Solar array with PCS-certified inverters
- Battery storage system to capture excess production
- CT meter at main service entrance
- PCS manages both solar production and battery charging to prevent exports
Typical Applications:
- Manufacturing facilities that want to maximize solar utilization
- Offices and retail with peak afternoon energy usage
- Any facility seeking energy resilience and cost optimization
Configuration 2: NEM Add-On (Hybrid Approach)
Best for: Existing NEM 1.0 or 2.0 customers wanting to expand
Setup:
- Keep existing NEM system unchanged
- Add new non-export system with separate PCS controls
- Dynamic power control ensures only legacy system exports
- Maximize onsite consumption with new capacity
Benefits:
- Preserve valuable NEM 1.0/2.0 rates on existing system
- Avoid AB 2143 on expansion capacity
- Optimal economics for most scenarios
Configuration 3: Subpanel Approach
Best for: Facilities with distinct electrical loads
Setup:
- Install new electrical subpanel for specific loads
- Non-export solar feeds only subpanel loads
- PCS prevents power flow from subpanel to main panel
- Requires electrical modifications but avoids UL 3141 certification
Compliance and Risk Management
Avoiding Common Pitfalls
Design Requirements:
- Size appropriately: System must be sized to onsite loads, not maximum roof capacity
- Proper documentation: Maintain records proving non-export configuration
- Professional installation: Use contractors familiar with PCS systems
- Ongoing monitoring: Verify system maintains non-export operation
Regulatory Compliance:
- Submit non-export interconnection application (Rule 21, Screen I, Option 8)
- Pay higher interconnection fee ($800 vs $145)
- Maintain manufacturer specifications for PCS operation
- No NEM program participation
Long-term Considerations
Advantages:
- Predictable costs: No prevailing wage compliance burden
- Rate protection: Immune to NEM program changes
- Faster approval: Simplified interconnection process
- Operational control: Full system ownership and operation
Limitations:
- No export credits: Cannot sell excess production to utility
- Higher fees: Increased interconnection application costs
- Sizing constraints: Must match onsite consumption patterns
- Equipment requirements: Limited to PCS-certified products
Industry-Specific Applications
Manufacturing and Industrial
Ideal Candidates:
- Consistent daytime energy usage >75% of solar production
- High demand charges (>$10/kW/month)
- Process loads that operate during solar production hours
Example: 750kW system for aerospace manufacturer
- AB 2143 cost: $937,500 + $93,750 = $1,031,250
- Non-export cost: $937,500 + $18,000 = $955,500
- Savings: $75,750 (7.3% reduction)
Retail and Hospitality
Considerations:
- Variable load patterns may reduce non-export viability
- HVAC loads align well with solar production
- Multiple locations can benefit from standardized approach
Example: Shopping center with 300kW system
- Peak usage during business hours matches solar production
- AB 2143 avoidance saves $30,000-45,000
- ROI improvement of 8-12 months
Healthcare and Education
Benefits:
- Predictable operational hours align with solar production
- Mission alignment with sustainability goals
- Budget certainty without compliance risks
Current Market Landscape and Strategy
Why Now Is the Right Time
Policy Stability:
- Non-export exemption has proven reliable since AB 2143’s implementation
- Utility interconnection processes now well-established
- Equipment certification widely available from major manufacturers
Market Advantages:
- Federal incentives remain at 30% through 2032
- PCS technology has matured with reliable, cost-effective options
- Clear competitive advantage over AB 2143-subject projects
Strategic Recommendations
- Evaluate early: Assess non-export viability during initial planning
- Size conservatively: Design for actual consumption, not maximum capacity
- Choose certified equipment: Use only UL 3141 certified PCS systems
- Professional design: Work with contractors experienced in non-export systems
- Document thoroughly: Maintain records for regulatory compliance
Getting Started: Your Non-Export Assessment
Initial Feasibility Analysis
Data Requirements:
- 12 months of interval energy usage data
- Peak demand patterns and timing
- Current electricity rate schedule
- Available roof or ground space for solar
Key Metrics:
- Daytime usage ratio: Percentage of total consumption during solar hours
- Load factor: Consistency of energy demand throughout the day
- Demand charge exposure: Monthly peak demand costs
- Rate escalation: Historical utility rate increases
Professional Design Process
- Energy audit: Analyze consumption patterns and solar production potential
- PCS specification: Select appropriate certified power control systems
- Electrical design: Plan CT placement and system integration
- Interconnection application: Submit non-export Rule 21 application
- Installation management: Ensure proper PCS configuration and testing
Conclusion: Smart Solar Strategy for 2025
AB 2143 has created a two-tier market for commercial solar in Southern California. Businesses that understand and leverage non-export systems can achieve:
• 10-15% cost savings compared to AB 2143-subject projects
• Simplified compliance without prevailing wage requirements
• Faster project timelines with streamlined interconnection
• Predictable costs without regulatory compliance risks
The key is acting strategically: Non-export systems aren’t suitable for every project, but for businesses with appropriate load profiles, they offer a compelling path to solar adoption without the AB 2143 penalty.
Next Steps
To determine if non-export solar is right for your Southern California business:
- Request a load analysis using 12 months of utility bills
- Evaluate your daytime consumption patterns during solar production hours
- Compare total project costs including AB 2143 impacts
- Review equipment options for PCS-certified systems
- Develop implementation timeline to optimize incentives and approvals
The commercial solar landscape has changed, but smart businesses can still achieve excellent returns by understanding their options and choosing the right approach for their unique situation.
Don’t let AB 2143 derail your solar plans - explore whether non-export systems can deliver the savings and sustainability benefits your business needs.
Related Resources
Our Services
Service Areas
Frequently Asked Questions
What is AB 2143 and how does it affect commercial solar costs?
AB 2143 is a California law effective January 1, 2024, requiring prevailing wage rates for most commercial solar installations over 15kW connected to investor-owned utilities (SCE, PG&E, SDG&E). This increases project costs by approximately 10-15% due to higher labor rates and compliance requirements.
How can businesses legally avoid AB 2143 prevailing wage requirements?
The primary legal exemption is installing non-export solar systems that don't participate in Net Energy Metering (NEM). These systems use power control systems (PCS) to ensure no electricity is exported to the grid, qualifying them for AB 2143 exemption.
What are non-export solar systems and how do they work?
Non-export solar systems use certified power control systems (PCS) that monitor power flow and shut down solar production within 2 seconds if electricity would flow to the grid. All solar power is consumed on-site, avoiding NEM participation and AB 2143 requirements.
Are there any downsides to non-export systems compared to traditional NEM systems?
Non-export systems have higher interconnection fees ($800 vs $90-145) and cannot sell excess power back to utilities. However, for businesses with high daytime energy usage, the 10-15% cost savings from avoiding prevailing wage often outweigh these limitations.